Show work center load and calendars in Graphical Scheduler

For production planners who want to see capacity and shift times on the same screen as the operations they schedule.

Recorded September 14, 2020 · 5 minutes

Graphical Scheduler data sources video thumbnail

Summary

Graphical Scheduler shows production order routing lines by default, and data sources add more to the same view. This is a completely free app from Insight Works for Business Central. The video adds work center load to see where capacity is free or full, and calendar entries to see when each shift starts and ends. It then drags an operation into a time with no capacity, and Business Central moves it to the next available time.

Key topics

  • Show simulated and released routing lines from separate data sources
  • Add work center load to see free capacity
  • Add calendar entries to see shift start and end times
  • Business Central moves an operation to the next available time
Read the transcript

The Graphical Scheduler by default is going to be showing your production order routing lines. You can change the information that shows. To do that, let’s navigate to View and we’re going to choose Edit.

In our example, we have two different data sources, and they’re both looking at production order routing lines. We have one for simulated, where we’re allowed to drag and drop with allow writes, and we have one for released production order routing lines, where it’s read only. This will show us two pieces of information at the same time and allow only the ones that are simulated to be dragged and dropped.

You can also add other information. For example, we have shop calendar holidays, or you could do work center calendar entries or work center load. Let’s explore some of these. If we wanted to see work center load, we would choose OK and it’ll create a new data source for us. Now we can see the load in action. For example, we can see that Sunday has no available capacity. We can see that there is work available on Friday, and on Saturday there’s available capacity and nothing planned.

You can also show calendar entries. In this case, if we wanted to understand more information about the capacity availability, if we show the calendar entries, we can see that the shift starts at 1 AM and ends at 10 PM. We’re also going to notice that the calendar entry is actually detailed to the availability. Let’s zoom back in so we can see that the shift ends at 10 o’clock. So if we were to drag and drop something where there’s no available capacity, we’ll probably see it move on to another day, and that’s exactly what happened. Business Central automatically moved this to the next available time.

If you want to have some information writable, for example production order routing lines, you can also make sure that that’s limited based on the filter. That’s how you can show other information in the Graphical Scheduler.

Questions about this webcast?