Project Map

Updated October 24, 2025

marks the party responsible for each task. T&M means the work is billable on a time and materials basis.

Step 1: Project Prerequisites (select app)

Warehouse Insight

Warehouse Insight: tasks and the party responsible
ItemDescriptionParty responsible
PartnerClientInsight Works
1.1Warehouse Insight Training Prerequisites
1.1.1Identify warehouse processes.Partner: yesClient: yesInsight Works: no
1.1.2Business Central: Configure, implement and training on the base Warehouse module.Partner: yesClient: yesInsight Works: no
1.1.3Business Central: Test base Dynamics NAV or Business Central Warehouse module by posting relevant transactions (picks, shipments, receipts, etc.)Partner: yesClient: yesInsight Works: no
1.1.4Business Central: Verify base Warehouse module has test data.Partner: yesClient: yesInsight Works: no

Please Note: If the client plans to use scanners to count lot or serial-tracked items, or to perform counts in directed pick and put-away locations, they must also license Advanced Inventory Count.

Dynamic Ship / LTL

Dynamic Ship / LTL: tasks and the party responsible
ItemDescriptionParty responsible
PartnerClientInsight Works
1.2Dynamic Ship Training Prerequisites
1.2.1Set up EasyPost account.Partner: yesClient: yesInsight Works: no
1.2.2Business Central: Verify sales order is ready to ship as test data (if not using warehousing).Partner: yesClient: yesInsight Works: no
1.2.3Business Central: Verify Warehouse shipment is created, picked, and ready to ship (if using warehousing).Partner: yesClient: yesInsight Works: no
1.2.4Identify if Freight and Parcel Carrier Connectors for Dynamic Ship are required. Additional licensing may apply.Partner: yesClient: yesInsight Works: no
1.2.5Review LTL Shipping Prerequisites and Considerations if using LTL.Partner: yesClient: yesInsight Works: no

Please note: If requesting a new or custom shipping integration, custom development may be required and will extend scope and timeline.

Shop Floor Insight

Shop Floor Insight: tasks and the party responsible
ItemDescriptionParty responsible
PartnerClientInsight Works
1.3Shop Floor Insight Training Prerequisites
1.3.1Identify Manufacturing processes.Partner: yesClient: yesInsight Works: no
1.3.2Business Central: Configure, implement and train on the base manufacturing modules.Partner: yesClient: yesInsight Works: no
1.3.3Business Central: Set up resources (if using time for Projects).Partner: yesClient: yesInsight Works: no
1.3.4Business Central: Ensure Projects can be created and Projects Journals can post resource costs to them (if using time for jobs).Partner: yesClient: yesInsight Works: no
1.3.5Business Central: Ensure released production orders can successfully post time, output, and consumption without errors.Partner: yesClient: yesInsight Works: no
1.3.6Business Central: Ability to post with the Output Journal.Partner: yesClient: yesInsight Works: no
1.3.7Business Central: Ability to post with the Consumption Journal.Partner: yesClient: yesInsight Works: no
1.3.8Business Central: Verify that relevant test data created.Partner: yesClient: yesInsight Works: no

Product Configurator

Product Configurator: tasks and the party responsible
ItemDescriptionParty responsible
PartnerClientInsight Works
1.4Product Configurator Training Prerequisites
1.4.1Identify sales processes (if using with sales documents).Partner: yesClient: yesInsight Works: no
1.4.2Identify production order processes (if using with production orders).Partner: yesClient: yesInsight Works: no
1.4.3Business Central: Set up component items and work centers (if using with production orders).Partner: yesClient: yesInsight Works: no
1.4.4Business Central: Set up sample production BOMs and routings to support production order processes (if using production orders).Partner: yesClient: yesInsight Works: no
1.4.5Business Central: Ensure released production orders can be processed using sample data and the results from posting meet both operational and costing requirements (if using production orders).Partner: yesClient: yesInsight Works: no
1.4.6Identify assembly order processes (if using with assembly orders).Partner: yesClient: yesInsight Works: no
1.4.7Business Central: Set up component items and resources (if using assembly orders).Partner: yesClient: yesInsight Works: no
1.4.8Business Central: Set up sample assembly BOM(s) to support assembly order processes (if using assembly orders).Partner: yesClient: yesInsight Works: no
1.4.9Business Central: Ensure assembly orders can be processed using sample data and the results from posting meet both operational and costing requirements (if using assembly orders).Partner: yesClient: yesInsight Works: no

Please note: We provide training to your key users on how to use the Product Configurator tool. You will be responsible for building and maintaining your own configurations.

Enhanced Planning Pack

Enhanced Planning Pack: tasks and the party responsible
ItemDescriptionParty responsible
PartnerClientInsight Works
1.5Enhanced Planning Pack
To use the Enhanced Planning Worksheet component of Enhanced Planning Pack you must:
1.5.1Ensure your Manufacturing Setup is complete (especially the Numbering and Planning FastTabs).Partner: yesClient: yesInsight Works: no
1.5.2Ensure your Business Central item or SKU planning parameters are setup.Partner: yesClient: yesInsight Works: no
1.5.3Ensure you have a forecast setup if you will be using one.Partner: yesClient: yesInsight Works: no
1.5.4Ensure you can run the standard Business Central Planning Worksheet and planning suggestions are created.Partner: yesClient: yesInsight Works: no
1.5.5If planning to use this it is probably best if users have already received training on the base Business Central Planning Worksheet or at least be familiar with how Business Central’s MRP works.Partner: yesClient: yesInsight Works: no
In order to use the Enhanced Forecasting Worksheet:
1.5.6You will need sufficient item ledger entries of type sale (the system uses the Posting Date, Item, and Quantity).Partner: yesClient: yesInsight Works: no
1.5.7Ensure the forecasting model setup has been completed.Partner: yesClient: yesInsight Works: no
Additional requirements:
1.5.8In order to use the Item Planning Review you will need sufficient item ledger entries.Partner: yesClient: yesInsight Works: no
1.5.9In order to use the Routing Analysis you will need to have routings setup along with having posted production times through the output or production journals and also finished production orders.Partner: yesClient: yesInsight Works: no
1.5.10In order to use the Multi-Level BOM Viewer you will need to have created production bills of material.Partner: yesClient: yesInsight Works: no

MxAPS

MxAPS: tasks and the party responsible
ItemDescriptionParty responsible
PartnerClientInsight Works
1.6MxAPS Training Prerequisites
1.6.1Business Central: Ensure work centers and shop calendars are setup.Partner: yesClient: yesInsight Works: no
1.6.2Business Central: Ensure machine centers are created for any work centers that have a capacity of more than 1.Partner: yesClient: yesInsight Works: no
1.6.3Business Central: Ensure routings are setup and contain setup and/or run times.Partner: yesClient: yesInsight Works: no
1.6.4Business Central: Ensure production bills of material are setup if necessary.Partner: yesClient: yesInsight Works: no
1.6.5Business Central: Ensure released production orders can successfully post time, output, and consumption without errors.Partner: yesClient: yesInsight Works: no
1.6.6Business Central: Ensure that a representative amount and item mix of production orders have been created.Partner: yesClient: yesInsight Works: no

View MxAPS Project Information Page

Counter Sales

Counter Sales: tasks and the party responsible
ItemDescriptionParty responsible
PartnerClientInsight Works
1.7Counter Sales Training Prerequisites
1.7.1Identify sales process.Partner: yesClient: yesInsight Works: no
1.7.2Business Central: Configure, implement and train on the base Sales module. Post test transactions: shipments, invoices, return receipts, credit memos.Partner: yesClient: yesInsight Works: no
1.7.3Business Central: If required configure, implement and train on the base Warehouse module. Post test transactions: picks, shipments, receipts, etc.Partner: yesClient: yesInsight Works: no
Counter Sales Payment Provider (credit card) integration prerequisites (optional)
1.7.4Determine which payment provider will be used and whether an integration is available. For a list of supported Counter Sales integrations, see Credit Card Processors.Partner: yesClient: yesInsight Works: no
1.7.5For available integrations, if not already done, please notify Insight Works if credit card integration services will be required.

Note: If credit card integration services are not included in your fixed-price project, support will be billed separately on a time and materials basis.
Partner: yesClient: yesInsight Works: no
1.7.6Confirm with the provider and Insight Works that the available integration supports your required functionality and hardware, as this can vary by region and integration.Partner: yesClient: yesInsight Works: no
1.7.7Acquire hardware and finalize setup with the provider.Partner: yesClient: yesInsight Works: no
Please note: If requesting a new or custom Payment Provider Integration, custom development may be required and will extend scope and timeline.

Quality Inspector

Quality Inspector: tasks and the party responsible
ItemDescriptionParty responsible
PartnerClientInsight Works
1.8Quality Inspector Training Prerequisites
1.8.1Identify internal quality processes and requirementsPartner: yesClient: yesInsight Works: no
1.8.2Business Central: Verify that the base modules where you plan to create inspection tests are configured and working as expected.Partner: yesClient: yesInsight Works: no

Please note: We provide training to your key users on how to create and use Quality Inspector. You will be responsible for building and maintaining your own Inspections.

Maintenance Manager

Maintenance Manager: tasks and the party responsible
ItemDescriptionParty responsible
PartnerClientInsight Works
1.10Maintenance Manager Training Prerequisites
1.10.1Business Central: Configure, implement and train on the base item and finance modules (standard cost).Partner: yesClient: yesInsight Works: no
1.10.2Identify Manufacturing processes.Partner: yesClient: yesInsight Works: no
1.10.3Business Central: Configure, implement and train on the base manufacturing modules.Partner: yesClient: yesInsight Works: no
1.10.4Business Central: Ensure work centers and shop calendars are setup.Partner: yesClient: yesInsight Works: no
1.10.5Business Central: Ensure released production orders can successfully post time, output, and consumption without errors.Partner: yesClient: yesInsight Works: no
1.10.6Business Central: Ability to post with the Production Journal, Output Journal, and Consumption Journal.Partner: yesClient: yesInsight Works: no

Other Apps

Other Apps: tasks and the party responsible
ItemDescriptionParty responsible
PartnerClientInsight Works
1.9Training Prerequisites
1.9.1Define relevant business processes.Partner: yesClient: yesInsight Works: no
1.9.2Business Central: Verify that the base modules affected are configured and working as expected.Partner: yesClient: yesInsight Works: no

Step 2: Project Initiation

Step 2: Project Initiation: tasks and the party responsible
ItemDescriptionParty responsible
PartnerClientInsight Works
2.1Place software order with Insight Works.Partner: yesClient: yesInsight Works: no
2.2Complete kickoff documents.Partner: yesClient: yesInsight Works: no
2.3Order scanners from Insight Works if required.Partner: noClient: yesInsight Works: yes
2.4Create Insight Works project ticket (use this ticket for all install/setup communication).Partner: yesClient: yesInsight Works: yes
2.5Schedule discovery via the provided links (1 to 2 weeks before training).Partner: yesClient: yesInsight Works: no
2.6Schedule training via the provided links (1 to 2 weeks after discovery).Partner: yesClient: yesInsight Works: no

Step 3: Set Up Existing Environment

Step 3: Set Up Existing Environment: tasks and the party responsible
ItemDescriptionParty responsible
PartnerClientInsight Works
3.1Update the Dynamics NAV or Business Central license with Insight Works products (On Premises Only).Partner: yesClient: yesInsight Works: no
3.2Provide Insight Works with administrative access (On Premises Only).Partner: yesClient: yesInsight Works: no
3.3Provide a user account with super user access to Insight Works.Partner: yesClient: yesInsight Works: no
3.4Provide remote access to test/staging Environment via install ticket (use www.isafesend.com for passwords).Partner: yesClient: yesInsight Works: no
3.5Provide remote access to on premises service server (only if On Premises Warehouse Insight and or using IIS).Partner: yesClient: yesInsight Works: no
3.6Provide remote access to on premises service server (always Shop Floor Insight).Partner: yesClient: yesInsight Works: no

Step 4: Review of Existing Environment

Step 4: Review of Existing Environment: tasks and the party responsible
ItemDescriptionParty responsible
PartnerClientInsight Works
4.1Verify remote access.Partner: noClient: noInsight Works: yes
4.2Verify administrative access (On premises only).Partner: noClient: noInsight Works: yes
4.3Verify Business Central super user access.Partner: noClient: noInsight Works: yes
4.4Verify service account licensing/users (require User or Device License).Partner: yesClient: yesInsight Works: yes
4.5Address possible issues with environment via project ticket (see Step 2).Partner: yesClient: yesInsight Works: yes

Step 5: Insight Works Products Implementation and Configuration

Step 5: Insight Works Products Implementation and Configuration: tasks and the party responsible
ItemDescriptionParty responsible
PartnerClientInsight Works
5.1Install Insight Works products.Partner: noClient: noInsight Works: yes
5.2Identify/merge conflicting Business Central modifications (if required).Partner: noClient: noInsight Works: yes
5.3Configure product on the test/staging environment.Partner: noClient: noInsight Works: yes
5.4 to 5.6: Warehouse Insight only
5.4Configure scanner and or emulator.Partner: yesClient: yesInsight Works: yes
5.5Train customer IT staff remotely to connect scanner devices when they arrive on-site.Partner: noClient: noInsight Works: yes
5.6Verify any label printers are working (any configuration / troubleshooting is billable T&M).Partner: yesClient: yesT&M (Insight Works, billable time and materials)

Step 6: Insight Works Discovery

Step 6: Insight Works Discovery: tasks and the party responsible
ItemDescriptionParty responsible
PartnerClientInsight Works
Discovery will need to be rescheduled if the pre-requisites have not been completed (see Step 1).
6.1Warehouse Insight (required).Partner: yesClient: yesInsight Works: yes
6.2Dynamic Ship (required).Partner: yesClient: yesInsight Works: yes
6.3Shop Floor Insight (required).Partner: yesClient: yesInsight Works: yes
6.4Identification of modifications (if required).Partner: yesClient: yesInsight Works: yes

Step 7: Insight Works Product Training (Train the Trainer)

Step 7: Insight Works Product Training (Train the Trainer): tasks and the party responsible
ItemDescriptionParty responsible
PartnerClientInsight Works
7.1Product training and Consulting.Partner: noClient: yesInsight Works: yes
7.2Identify modifications (support request).Partner: noClient: yesInsight Works: yes
Important Reminder for Project Managers: Prior to the training sessions, ensure that either an emulator or scanner is fully set up and ready for use.

Step 8: Product Modifications (if required)

View the Custom Modifications Process

Step 8: Product Modifications (if required): tasks and the party responsible
ItemDescriptionParty responsible
PartnerClientInsight Works
8.1Requirements & Design Phase (1 to 3 weeks depending on resources) (billable T&M).Partner: noClient: noT&M (Insight Works, billable time and materials)
8.2Development Phase (1 to 3 weeks depending on resources) (billable T&M).Partner: noClient: noT&M (Insight Works, billable time and materials)

Step 9: UAT Phase

Step 9: UAT Phase: tasks and the party responsible
ItemDescriptionParty responsible
PartnerClientInsight Works
9.1Develop test case scenarios.Partner: yesClient: yesInsight Works: no
9.2Conduct user testing based on test scenarios.Partner: yesClient: yesInsight Works: no
9.3Insight Works will provide UAT support as required (support request).Partner: yesClient: yesInsight Works: yes
9.4Identify modifications (support request).Partner: yesClient: yesInsight Works: yes
9.5Submit go-live ticket (support request) (requires 5 business days’ notice).Partner: yesClient: yesInsight Works: no

Step 10: Go Live

Step 10: Go Live: tasks and the party responsible
ItemDescriptionParty responsible
PartnerClientInsight Works
10.1Move Insight Works product objects from the test system to the production system.Partner: noClient: noInsight Works: yes
10.2Move Insight Works product configuration from the test system to the production system.Partner: noClient: noInsight Works: yes
10.3Reconfigure service tier or install a new service tier (dependent on the client’s server setup).Partner: noClient: noInsight Works: yes
10.4Reconfigure the devices to refer to the new company and service tier.Partner: yesClient: yesInsight Works: yes
10.5Conduct a smoke test with the devices to verify connectivity with Business Central.Partner: noClient: yesInsight Works: yes
10.6Post Go-Live Support (billable T&M).Partner: yesClient: yesT&M (Insight Works, billable time and materials)