Skip to content

Shop Floor Insight

Actual labor time being added to expected time

Viewing 4 posts – 1 through 4 (of 4 total)
  • Author
    Posts
  • #8501
    Mathew B.

    Our client has started entering expected Run Time quantities against the routings. Now when they post the actual time captured by the workers against the production order, the actual time captured as well as the Run Time quantity on the Routing is being posted. Is there a way that they can have the Run Time quantity on the Routing as the expected time only and have the actual time entered only post to the production order so that they can compare actual versus expected?

    #9951
    Terri V.
    Insight Works

    Hello Mathew,

    Indeed, when you post the Shop Floor time cards this will post the times on the time cards lines to the capacity ledger entries of the corresponding released production order. This is the actual labour time of the Shop Floor employees.

    I do know it is possible for the expected run times to also be posted or “flushed” – I am referring to the values you will see when looking at the routing lines on the production order under run time, and possibly also setup time.

    This is however a BC configuration, not anything specific to Shop Floor Insight.

    I would recommend you speak to your colleagues on how this can be disabled so that only the time on the Shop Floor time cards is posted to the production orders and not have the automatic flushing of the expected run times also post.

    From our KB site, an article on how to post Shop Floor Insight time cards: https://kb.dmsiworks.com/knowledge-base/posting-shop-floor-data-in-shop-floor-insight/.

    From Microsoft, a page on production orders and flushing: https://learn.microsoft.com/en-us/dynamics365/business-central/production-about-production-orders.

    As for the comparison of the actual VS expected run times, this is something that can be done with some reports in BC. I would recommend using the entries in the Capacity Ledger entries for the actual time and the production order routing lines for the expected time.

    Thank you,

    #10426
    Mr. S.

    Terri – I know this is an older topic; however, I wanted to confirm something.

    If we set a Run Time on a Routing Line, when we capture time (which drives costs) against the routing line it will add the Labor Costs & the Est. Time, which results in potentially 2x the costs, assuming the work is completed in the exact amount of time that we estimated.

    Seems like this would be an issue for everyone, is there any other way around this?

    #10428
    Terri V.
    Insight Works

    Hello Mr. Scribner,

    If you are seeing the estimated Run time and estimated Setup time post to the Capacity Ledger Entries and this is in addition to the time recorded on the Shop Floor time cards, this is likely because of some BC configuration. Perhaps you have the flushing method of the BC Work Center or Machine Center set to something other than ‘Manual’? There could also be other reasons.

    To confirm this, if you look at the CLE for the production order, you will see a few fields specific to Shop Floor Insight. I’ve listed a few below:

    SFI Shop Floor Employee No.
    SFI Employee Name
    Time Card No.
    Time Card Line No.

    If you tracked labour time from a SF time card and posted it, then you should always have some information in all four of these fields. One CLE entry for each unique time card line referencing a released production order. If however you posted time to the production order outside of a SF time card, then you will NOT have any information in these fields. This also would confirm that this is either a BC user posting time in the Output journal, or perhaps some automatic flushing of labour time or something else in BC.

    In this case you need to review the BC configuration and change it so you are only tracking labour time on production orders from the SF time cards.