Work Center Setup Time Change Work Around

Viewing 4 posts – 1 through 4 (of 4 total)
  • Author
    Posts
  • #8649
    Devon K.

    I need to somehow change the setup time of a work center for our configurator. I know that changing the setup time directly is not possible. How can I work around this?

    I have one work center for Wire Length with two choices, kanban and custom. Both choices have different setup times. I’d like to keep one work center for either choice, Wire Processing Work Center. This is what I tried so far:

    In the Configurator Routing, Wire Processing Work Center is called out two times as Operation 10 and Operation 11. Operation 10 and 11 both have different setup times but are applied to the same work center. When I run the configurator and I select to have kanban wire for my Wire Length choice, I ultimately get both work centers and both setup times for Operation 10 and 11 on my final product routing.

    I must be missing something because I need only one of the two Operations to show up in the final routing. Did I set this up wrong or is there a way to turn off an Operation from showing on the final product routing?

    Thank you

    #10251
    Jessica M.
    Insight Works

    Hello,

     

    Based on the information above, it sounds like you will need to set the operations up as choices. That way, when the user is configuring the item, they will only have the applicable operation selected.

     

    Thank you!

    #10254
    Devon K.

    Hello Jessica,

    Thank you for the reply. Are all work centers supposed to show up on the final routing by default? Because I have operations within work centers that are embedded in Choices within the configurator and even when none of those choices with the operations are selected, all work centers are visible on the routing. My goal is to have the routing be custom made for the part and based on the choices, some work centers will show and some will not. Can the configurator handle this or do I need separate routings called out to do this?

    #10275
    Jessica M.
    Insight Works

    Hello,

    One way you can go about setting a specific Work Centre (as opposed to being able to see all of them) is by setting up Option Choices with Type=Operation. This will add the operation to the routing (operations can be either Work Centres or Machine Centres).

    You would have an Option Choice (or Choices) with Type=Operation to add the operation (either 10 or 11, or both). Those operations would just reference the same Work Centre.

    Thank you!