    Christer M.

    Hi.

    I have a scenario where my routing line defaults to a Work center. Then the Mx Planning engine will give me a result where it has found one of the corresponding machine centers to run the operation in.

    I’m looking for a setting to default that the operation is being planned in multiple machine centers simultaniously. If we can split the order/operation into five machines, that would correspond better to the planning we’re aiming for, where an operator can monitor five machines running the same operation at the same time.

    Any high level help would be appreciated!

    #10689
    Terri V.
    Insight Works

    Hello Christer,

    This can be done on the Master Routing line on the added fields from MxAPS.

    Ensure the Routing Line BC field “Concurrent Capacity” is set to the corresponding number of how to split and then set the Routing Line MxAPS fields “No. of Lots” to corresponding amount, “Enable Transfer Lots” to “Use Concurrent Capacity” and “Max. Machines” to corresponding amount.

    Instead of using concurrent capacity, you could also split by a batch size and then set the “Enable Transfer Lots” to “Specific Lot Size” and then set “Transfer Lot Size” to the corresponding amount.

    Please submit a support request to su*****@*******ks.com for further assistance.