Scheduling only first operation

Viewing 2 posts – 1 through 2 (of 2 total)
  • Author
    Posts
  • #8667
    Aki K.

    Hi,

    What setting could be wrong that MxAPS only schedules the first operation line on the Routing or leaves the last Routing Line away from scheduling?

     

    #10294
    Terri V.
    Insight Works

    Hello Aki,

    On the routing line please check that the below fields are populated:

    • “Run Time” or “Setup Time” – values populated in one or both (not MxAPS does not schedule wait or move time)
    • “Schedule Behaviour” – set to Include
    • “Secondary Constraints” – not necessarily required but this setting will determine if other factors in play for example:
      – if set to “Do Not Schedule” then this should just schedule based on machine/work center capacity
      – if set to “Schedule” then this will require any sort of additional constraint based on advanced setup or component requirements if routing link codes are different   than other operations.

    This is also required as “Schedule” if this production order is producing a semi-finished product that will be required for a subsequent production order.

    Also, ensure that there is sufficient capacity on the work center/machine center specified

    If you would like a further review please submit a ticket to su*****@*******ks.com and we can help out with your specific situation.

    Thank you,