Production Scheduling

Viewing 4 posts – 1 through 4 (of 4 total)
  • Author
    Posts
  • #8500
    Todd M.

    We have found that that MXAPS likes to schedule productions as close as possible to the production due date.  We would like to find a way that if the raw material is in inventory, mxaps will schedule the builds.  We have done this with priorities, but some of the stuff isn’t a priority and we would like mxaps to move the productions sooner because we have the parts to build.

    #9950
    Terri V.
    Insight Works
    Hello Todd,
    As a forward scheduler MxAPS is scheduling to complete orders as early as possible.  
    Due Date only factors into this if it is part of the user defined Scheduling Rule, which determines the sequence MxAPS considers the Operations for scheduling in.
    Please also reference our Knowledge Base regarding MxAPS Scheduling Rules: Scheduling Rule Card – Insight Works Knowledge Base
    Thank you,
    #9953
    Todd M.

    Does anyone have a suggested rules set that they use and have seen good success with scheduling?

    Ours:

    10 Priority

    20 Due Date

    30 Order Number

    40 Order Attribute Key

     

    We haven’t changed these from default and that might be some of our problem with scheduling.

    #9954
    Terri V.
    Insight Works

    Hello Todd,

    Scheduling rules are generally customer specific and are meant to provide a sequence for the scheduling engine to consider when reviewing all the supplied orders.

    If you are having specific concerns around how to get the anticipated results, please submit a ticket to su*****@*******ks.com. Then we will be able to connect and review your environment and situation.

    Thank you,