7 May 2025 at 10:44 am #8699MSMr. S.
We are new users to Shop Floor Insight, and have been able to test thoroughly and are about to go live. Everything has worked as expected, EXCEPT the “Overtime Factor”. We have reviewed the content here: https://kb.dmsiworks.com/knowledge-base/configure-paycodes-in-shop-floor-insight/
and have set everything up using (1) as the factor on Regular Pay and (1.5) on Overtime. We require the use of Direct Unit Cost, Indirect % and Overhead Rate on our Work Centers; however, when setting the system up it is NOT multiplying the Direct Unit Cost by the factor of 1.5, it is adding $1.50 to each transaction.
Working with out implementer a work around was suggested; however, it feels to me that we are missing a setting or there is a code issue. Any thoughts?
8 May 2025 at 7:20 am #10369TVTerri V.Insight WorksHello Pete,
It is only possible to see any cost increase on production orders for Daily OT scenarios. This is because the weekly OT cannot identify what production orders get OT. Unless you are bringing changes to the time cards before you post them to indicate the OT paycode, but normally the OT adjustments occur via the payroll adjustment worksheet.
You need to be configured in a specific way to see the cost impact on production orders for any OT.
In order to see any cost increase for any daily OT time against production orders you will need the following:
SF setup
POST OVERTIME COST = ON
USE DIRECT LABOR COST FROM = SF EMPLOYEE *or* SF WORK CENTERSF employee card
SOURCE TYPE = EMPLOYEE or Resource or Blank (whenever cost is using SF employee)
when SF setup is using SF WC as cost, need to have the source type of the employee = WC and cost set in SF WC.PAYCODES
Ensure that the OT paycode has the correct Overtime factor, usually 1.5SF PAYROLL RULE CONFIG
Ensure the “Use Source Line Details” set to ONThe OT portion will be determined on how the SF setup is configured and either use the cost of the employee * 1.5, or the cost of the SF WC * 1.5.
If you have any further question, might be best to send us an email to su*****@*******ks.com.
Thank you,
-