    We saw a comment in another thread about the “planning period”.  We get the simplified planning engine that isn’t time phased, but we still would like to put (at minimum) an ending date.  The forecast seems to allow for that, but we really don’t want to plan to purchase items that have demand in the system 9+ months out especially if the items that do not have that long of a lead time.

    “Unlike base BC it generates a single supply order per SKU to cover the net shortage during the planning period.”

    How can we limit the planning period, so it only plans for demand thorough a certain date?

     

     

    #10554
    Terri V.
    Insight Works

    Hello Chuck,

    The ‘Calculate Purchase Plan’ isn’t time phased how you mentioned.

    By using the Forecast End Date, this would only factor in what is populated in a Demand Forecast and not Firm Demand.

    We would need to explore a custom development option for your environment to allow for this approach by adding an ‘End Date’ as described.

    Please submit a support request to su*****@*******ks.com for further assistance.