- This topic has 4 replies, 2 voices, and was last updated 1 year, 8 months ago by Roman H..
-
AuthorPosts
-
22 February 2025 at 4:45 pm #8653RHRoman H.
Hey there,
If configurated product’s standard routing (2-3 operations) run time is always affected (increasing) by the selected options.
Where every selected additional option adds items to the specific standard operation (using Prod. BOM) and the additional option also increases operation time (labor time).
Can configurator add to the standard routing, to the standard operation additional time, instead of overwriting it, if, for example, operation 20 and 30 are existing operations ?
24 February 2025 at 11:00 am #10258DKDevon K.Roman,
I had to recently do this workaround to add to the runtime to a single work center… It’s much easier to replace the runtime! But if you have to add to it with various operations then you need to setup the additional runtime as text in a new variable and then have a separate new variable to add the runtimes as text before it can be called out in another variable. It’s quite involved to add runtimes together. It would be much easier for me to screenshot images from my configurator to show you. If you share your email, I can send those to you. This forum doesn’t allow images for some reason.
24 February 2025 at 12:30 pm #10259RHRoman H.Hi Devon,
It would have been great to see some examples to solve this challenge.
Do not fully understand how would it be better by replacing standard runtime when I have up to 10 options to be selected. Each one option adds a bit of time to standard operations.
Just to be sure that we are on the same page, here is simple example:
Standard Operations (Base routing):
(Work center 100) Operation 1: Cutting => Standard Time: 3 hours
(Work center 200) Operation 2: Assembly => Standard Time: 2.5 hours
Options with Additional Time:
Option 1: Add a Drawer
Operation 1: Cutting => Additional Time: +0.5 hours
Operation 2: Assembly => Additional Time: +1 hour
Option 2: Add a Shelf
Operation 1: Cutting => Additional Time: +1 hour
Operation 2: Assembly => Additional Time: +1.5 hours
Result => which I am interested in having on the Production order:
(Work center 100) Total time for Operation 1 (Cutting Time) : 3 hours + 0.5 hours + 1 hour = 4.5 hours
(Work center 200) Total time for Operation 2 (Assembly Time) : 2.5 hours + 1 hour + 1.5 hours = 5 hours
By configuring product the additional time need to be sum with the standard time instead of replacing it.
27 February 2025 at 7:28 am #10268DKDevon K.Roman,
To add the runtimes you need to have separate variables, ie “Code” or Configurator Option, that are text.
So for your example, the runtime for the cutting, adding a drawer or shelf are all 3 separate variables saved as Text with the Child qty Calculation Formula as the runtime. Then have another final variable as the total runtime for the Cutting. That Total Cutting Runtime variable will be an Operation with number 100, and the Child qty Calculation Formula will be the 3 text variables for the runtimes added together, “BaseText + DrawerText + ShelfText. The default value for all 3 text variables will be 0, unless that option is selected of course. That way when any of the 3 are selected for the custom product, the runtime will be updated correctly. The configurator just doesn’t have the ability to add runtimes as anything but text so you need separate variables for all of this.
If you have further questions, you can drop your email and I can send you screenshots of how mine works.
3 March 2025 at 6:18 am #10269RHRoman H.Hi Devon,
I can’t get those text variables to work together properly. Could you please share your set up. Here is mail: ro*******@***il.com
-
AuthorPosts
- Sign in below to reply.