  • #8518
    Iuri R.

    <div>
    <p class=”x_MsoNormal”>I have been trying recently to set up scheduled daily runs for our Enhanced Planning Worksheets, but I didn’t succeed.</p>

    </div>
    <div>
    <p class=”x_MsoNormal”>Are there any functionally from Insight works side that can help us on this scheduled run?</p>

    </div>

    #9986
    Mark G.
    Insight Works

    Hi Iuri ,

    The Calculate Purchase Plan action can be added to a Job Queue if that calculation logic works for your environment.  As a note that Purchase Planning calculation was added by Insight Works and is probably most suitable for distribution type environments.  Unlike base BC it generates a single supply order per SKU to cover the net shortage during the planning period.  This allows it to run faster than the base BC calculation which is potentially having to create an Action Message for each demand line it encounters, however this comes at the cost of holding more inventory as the supply suggestion is created for the user’s Work Date so it front loads it.

    However, the other calculation methods in the Enhanced Planning Worksheet, such as the Calculate a Regenerative Plan, use the base BC functionality, and those will require development to be able to added to a Job Queue.  Your BC partner should be able to assist you with this as it is a base BC function.