Constraining the schedule against component availability

Viewing 4 posts – 1 through 4 (of 4 total)
  • Author
    Posts
  • #8901
    Nathanial M.

    Hi

    I am wondering how to config my Business Central such that for any production orders, they are constrained in the schedule by component availability.

    I am using routing link codes to link components to routing lines and thus the component due date matches the routing line operation start date.

    Lets say the component due date is 31.03.26. There is no current availability of the item. The production order routing line shouldn’t be scheduled and any follow on operations also unscheduled.

    If there is no current availability but there is a receipt due say 01/04/26 then the schedule waits until the component is available.

    Many thanks

    #10736
    Terri V.
    Insight Works

    Hello Nathanial,

    There are a couple of other settings that need to be setup to ensure the schedule gets constrained.

    First being that on the routing lines that each of the operations have the “Secondary Constraints” set to “Schedule”. Second being that on the item card for each of the constraints you have listed have the “Constraint Type” set to “Constrain” and “Fence Type” set to “Global” or “Item”.

    If “Fence Type” is set to “Item” MxAPS will use the Item’s defined Lead Time for when the item would be automatically replenished.

    If “Fence Type” is set to “Global” MxAPS will use the defined “Global Lead Time” which is set when generating a schedule.

    Then if you would like no auto replenishment, either set the “Global Lead Time” value to exceed the “Schedule Duration” or set the Item “Lead Time” to be greater than the maximum schedule duration of 365 days.

    Thank you,

    #10737
    Nathanial M.

    Thanks Terri, I have tried the above but the schedule is still putting the routing line at the earliest opportunity, it is still scheduling despite item not being available on the due date of the order.

    I even tried adding a reservation in and the schedule still moved the operation as early as possible.

    The item missing is currently on a purchase order due in on 2/4/26.

    The routing line operation is due 2/4/26.

    The schedule puts that operation at the earliest possible point of 1/4/26.

     

    I would have expected the operation linked to that component to not be scheduled until 2/4/26

    Interesting, whilst I have set the secondary contraint on the routing line, that field doesn’t appear on my prod order routing line table… tried personalisation and page inspection and not there.

    Please

     

    #10738
    Terri V.
    Insight Works

    Hello Nathanial,

    This will require some one on one support.

    Please submit a support request to su*****@*******ks.com for further assistance.

    Thank you,

Viewing 4 posts – 1 through 4 (of 4 total)