    We have client manufacture/sell designer chairs across states, and these chairs are setup as finished good items (approx. 200 different item codes for each type chairs), each chair has a pre-defined production BOM attached to it, however whenever customer place their orders, they need to choose color of fabrics want to use to produce this chair.

    As an example, CHAIR-001 (15 fabric color to choose), CHAIR-002 (10 fabric color to choose), CHAIR-003 (3 fabric color to choose) – please note except fabric color, rest of the bill of material required to make the chair are static (such as Frame, Wood, Glue etc.,), we need these 200 items to be created as individual item to configure the sales price for customers tool.

    How do I configure the product configurator in such a way, so first I can select FG code (CHAIR-001) then select the fabric color, so the sales line update with CHAIR-001?

    Based on my understanding, we have to create each CHAIR as a Quote Item in the Configurator Item Categories, then specify the choice options to list all the bill of material items as choice codes, only color choice will list of fabric color item to choose, this approach can become messy data maintenance point of view.

    Do you have any other alternative approach to achieve above results?

     

    #10601
    Terri V.
    Insight Works

    Hello Shankar,

    For this use case, we suggest creating the BOMs with the base components and setting that BOM as an Option Choice type Production BOM that can be selected from the configuration.

    This way you will retain the ability to choose fabrics/colors as their own separate Code and Option Choice selection, but have the ability to configure one finished good item from the BOM Designer.

    If you require more detail around the setup of functionality for this type of scenario, please submit a support request to su*****@*******ks.com for further assistance.

    Thank you,

    #10624
    Jon O.

    You may want to consider making a pre-configured BOM item for each option.  If you only have 1 Base Bom of 200 Styles X 15 (max) fabrics that would be a maximum of 3000 Items.  You can use the import / export feature, and or Configuration Packages to mass replicate.  This could be done in 1 day.  Keep the Routing No. the same for each item.  This way, if you need to edit the routing procedure for the chairs, it will replicate throughout.  Now all you need is to modify the Production BOM No. with the different styles of fabric.  Make sure each of those have a unique code.  Once completed, Sales will not need to spend the time to “Build” each item, they will simply be in your item list.  This is especially helpful if you wish to sell online and/or Shopify.  I am doing the same thing for our doors, except it’s more like 20 X 8 X 3 X 3 X 5 X 2 X 7 = 100,800.  Hope that helps.