  • #8706
    Dermot M.

    Hi, I have recently downloaded the free Graphical scheduler so thanks for offering it as a free app. The limitation I am having is that all operations from a works order run concurrently. I would like to have one operation finishing and then a break for a period depending on the availability of the next work centre before the next operation starts. Is this possible?

    Thanks

    #10370
    Terri V.
    Insight Works

    Hello Dermot,

    Graphical scheduler won’t automatically do this but will allow you to drag/drop to manually create this.

    To automatically create a production schedule like this you would need our scheduling product, MxAPS.

    Thank you,