11 December 2024 at 9:12 am #8601SKShane K.
Is there a way to write rules so that the product configurator can manipulate the bill of material scrap percentages? I’ve completed a nearly fully functioning configuration and now I cannot find a place to manage BOM scrap. I know I could build rules to have scrap added as a secondary line item of the component, but I would really prefer to manipulate the BC systems scrap percentage field rather than working around the issue.
11 December 2024 at 11:55 am #10168TVTerri V.Insight WorksHello Shane,
The Option Choices include the “Scrap %” field where you can specify a fixed value for the component item’s scrap percentage.
If the choice item is added to the configured item’s production BOM it will assign it this value. Note the field may not be visible on the page by default so you may need to first show it through personalization.
For reference: https://kb.dmsiworks.com/knowledge-base/configurator-option-choice/.
Thank you,
11 December 2024 at 1:54 pm #10169SKShane K.Terri,
Thank you, that is helpful. My scrap percentage is dependent on the quantity of the component in the BOM, which is a variable driven by a different option choice. Is there a way for me to manipulate the value of scrap percentage using an equation or a rule? Or maybe you have seen an instance similar to the example below and have insight on how others might be doing this?
I have a 10″ part that can be cut down. If I’m cutting down to 2″ then 10/2=5 so I should be able to get 5 parts out of that stick. In reality, the saw blade removes material such that I have to scrap the very last piece, so to do that I add a scrap percentage. If I’m cutting down to 5″ then I can only get 1 part out of the stick, and the rest needs to be scrapped against the BOM, but this is a different scrap percentage.
11 December 2024 at 2:53 pm #10170TVTerri V.Insight WorksHello Shane,
Unfortunately the “Scrap %” only accepts a fixed value. This calculated-value scenario has been brought before however at this time we have no plans to make any product changes, but it is something we will re-look at again in the future.
Here are a few approaches you can try:
- Set up the option choice so that it includes the net quantity required (e.g., the finished product may only require 5″ but if it results in the entire 10″ stick being used then have it configured for the BOM to require the 10″ quantity, you can use the Option Choice Comments to pass special instructions to the production order to inform the shop floor that the 10″ requirement on the BOM needs to be cut to 5″ with the remainder to be scrapped).
- Variation on (1), have multiple option choices where one calculates the required 5″ quantity and another where it calculates the remainder. This would result in 2 component lines for the same item however it allows you to facilitate consuming the required amount plus the scrap amount. You may also want to use the Option Choice Comments here to provide instruction to the shop floor to ensure the line with the cut 5″ is used in the product and the line with the remainder is consumed as scrap.
- Explore an extension. It should be possible to handle the scenario through special logic where is updates the “Scrap %” with the calculated value on the production BOM lines after being created.
Thank you,
12 December 2024 at 7:06 am #10172SKShane K.Thank you Terri,
The options you’ve mentioned here are a similar path to where I was going with a workaround. Having my thoughts confirmed by an expert always makes me feel better. I appreciate your time on this.
-