Consumption and Capacity Cost Detail for Microsoft Dynamics 365 Business Central
A total variance says a production order cost more than expected, but not whether the cause was material, time on the floor, or outside work. Production Order Analysis breaks production order cost in Business Central into material, labor, and subcontracting, using the consumption and capacity entries posted against the order.
Capacity cost is the cost of time at work centers, so it shows apart from the materials consumed.
How Consumption and capacity cost detail works in Production Order Analysis
- Open Production Order Analysis and select the production order.
- Read the component lines: expected and actual quantity and material cost.
- Read the work center lines: expected and actual setup and run times.
- Compare with the totals for each cost type.
- Follow up on the driver: material usage, time on the floor, or subcontracting.
Key capabilities
Component quantities
For each component, the worksheet shows quantity per, expected quantity, actual quantity, and the quantity variance.
Material cost per component
Single-level material cost shows expected cost, actual cost, and variance for each component, so a usage or price difference is traced to the part.
Times at each work center
Expected and actual setup and run times, with their variances and units of measure, appear for each work center on the order.
Subcontracting and overhead
Subcontracted cost and capacity overhead have their own figures in the totals, separate from material and capacity cost.
Find the driver
Reading quantities, times, and costs together shows whether a variance came from using more material, spending more time, or paying more for outside work.
See Consumption and capacity cost detail on screen
Real screens from Production Order Analysis, shown with demo data.
Details that matter on the floor
Times beside costs
Because routing times sit on the same worksheet as costs, a capacity variance can be traced to the setup or run time behind it. For time variance across every order that used a routing, Routing Analysis is the related app in the Enhanced Planning Pack.
Who uses Consumption and capacity cost detail
Cost accountants
Use the material, capacity, and subcontracting breakdown for cost allocation and variance review.
Production managers
See whether an overrun came from material or from time on the floor.
Supply chain managers
Use material cost detail to inform vendor management and future purchasing.
Questions about Consumption and capacity cost detail
Can Business Central break production order cost into material, labor, and subcontracting?
Yes, with Production Order Analysis. Production Order Analysis shows expected and actual material, capacity, subcontracted, and capacity overhead cost, with the variance for each.
Does Production Order Analysis show routing times?
Yes. Expected and actual setup and run times, with their variances, show for each work center on the order.
Is capacity overhead included?
Yes. Capacity overhead has its own expected, actual, and variance figures in the totals. Overhead and cost allocations are reported in the standard Business Central cost buckets.
Related Production Order Analysis features
All Production Order Analysis features →Part of Production Order Analysis
Monitor actual vs. expected production costs to optimize budgets and enhance profitability.
Have a question about Consumption and capacity cost detail?
Send us a note and the Production Order Analysis team will reply by email. Ready to plan a rollout? Contact your Microsoft Partner.