How do you create routings in Business Central?

Short answer

A routing lists the operations to make an item, in order, with the work center or machine center, setup time, and run time for each. You set up work centers and machine centers first, create the routing, certify it, and assign it to the item. Apps such as Routing Analysis compare planned times with what actually happens on the shop floor.

The steps

  1. Set up work centers, and machine centers where a work center has more than one machine, with their calendars and capacity.
  2. Create a routing and choose serial or parallel.
  3. Add operations in sequence, each with a work center or machine center, setup time, run time, and wait and move times.
  4. Link components to operations with routing link codes if materials are consumed at a specific step.
  5. Certify the routing, and assign it to the item.

Versions

Like BOMs, routings support versions with starting dates, so you can change a process without losing the history.

Checking routings against real production

Routing Analysis compares recorded run times with routing standards, so you can correct routings that are out of date on the same screen. Shop Floor Insight captures those times on the shop floor with barcode scanning.

Last reviewed against Microsoft documentation on October 27, 2026.