      Hi , I have just installed the Graphical Scheduler ,looks great so far

      We have a 3 stage Routing  , the scheduler is creating gaps in the first 2 processes to account for the overload on the 3rd process ,

      can this overload be ignored

       

      Terri Vaive
        Post count: 504
        Upvote
        Up
        0
        Down
        Not Helpful
        ::

        Hello Martin,

        If using the Data Source Table Name Prod. Order Routing Line, to display the Production Order Routing Line data then the Graphical Schedular will respect the Capacity and visualize accordingly while using the Time Scale of “Day and Week or “Hour and Day” for instance.

        You may see benefit from a adding a new View using our ‘Anything’ Feature Data Source to display the Prod. Order Line (5406) table instead as this will not show gaps as the entire Production Order Line will be plotted instead of each Production Order Routing Line.

        Another suggestion is to try out other Time Scales as others may be more beneficial depending on the type of data visualization that is required.

        Please see the following Knowledge Base Articles:

        1. Anything Feature in Graphical Scheduler
        2. Default a Time Frame in Graphical Scheduler.

        Thank you,

        • This reply was modified 1 week, 5 days ago by Terri Vaive.
        • This reply was modified 1 week, 5 days ago by Terri Vaive.
        • This reply was modified 1 week, 5 days ago by Terri Vaive.
      Viewing 2 posts - 1 through 2 (of 2 total)
      • You must be logged in to reply to this topic.