Home Forums Enhanced Planning Pack Multi Level Bom Viewer

Viewing 2 posts - 1 through 2 (of 2 total)
  • Author
    Posts
  • Stephen WoodheadStephen Woodhead
      Post count: 1

      Hi

      We have now installed your APP into out test system and are currently looking at the Multi Level BOM Viewer.  I have built a simple structure for testing.  I have established how to alter the Quantity Per on the Bom.

      Quick question

      • How do I add a new component into the BOM, say add item COMPONENT 6 into the BOM of SUB-ASS 2?
      • How do I delete a line in the BOM structure, say delete Component 4 from the Sub-Ass 1 BOM?

       

      Regards

      Steve

      Terri VaiveTerri Vaive
        Post count: 48

        Hello Stephen,

        The Multi-Level BOM Viewer only allows viewing the BOM and the editing of existing lines.

        If you want to add or delete lines you would be doing that using the base BC Production BOM page.

        Thank you,