Hi Boris,
The field you need is not on the page by default, so you’d need to use the Settings->Design option on the Shop Calendar Working Days page and add the “Available Resources” field to the view.
Also, I checked and you are correct, the lookup on that field in the Item card in the extension version you have is not pointing to the correct table. This has been corrected for the upcoming version 4.2 release which is in testing currently.