Home Forums MxAPS Machine operations planning based on available employees to operate the machines Reply To: Machine operations planning based on available employees to operate the machines

Mark GenglerMark Gengler
    Post count: 9

    Hi Boris,

    MxAPS has secondary constraints to represent things like labor and tooling.  The setup for that would be as follows:

    1)  You create a Shop Calendar and when defining the working days and times we have a added an additional field where you can specify the quantity of operators available.

    2)  Create an item to represent the pool of operators.  In the MxAPS FastTab assign it the Shop Calendar you just created, and set the constraint tracking to constrain based on the availability of the item.  You would also need to set the time period over which the constraint applies by making sure the Fence Type is set to item and then entering a duration in the Lead Time Calculation in the Replenishment FastTab (past this time the system is allowed to go negative, so if this should never happen use a large value like 999 days).

    3)  Assign the new item to a work center or machine center in the Machine Constraints page.  The From Segment and To Segment allow you to define when the operator is needed.  For example you may only need an operator during the Setup activity or you may need them from the Setup to the Run.  The Release Segment defines if and when the constraint item is replenished, which is typically the case for an operator or a tool, and is typically the same value as the To Segment.  Finally the Logic determines if a fixed quantity of the secondary constraint item is needed or if it depends on order quantity.