Schedule Result List / Schedule Results

You are here:

The MxAPS Schedule Result List page contains a list of the schedule results for any generated schedules. Some high-level performance metrics for each result are listed on this page and in the FactBox.

Beginning on this page, you can access more details on individual results and graph results. You can set a result as active and commit the active results to Business Central to update the starting and ending dates and times on production order routing lines.

Worth noting:

  • Multiple sets of results can exist simultaneously.
  • Only one result may be “Active” at once.
  • The “Active” schedule appears in bold.
  • An “Active” schedule can be “Committed” to Business Central, which will update the starting and ending date times on the related Production Order Routing Lines.

Schedule Result List Tooltips

Field/Control Name FastTab or FactBox Caption Tooltip
Schedule Result No. Schedule Result No. Specifies the No. of the result.
Scheduled By Scheduled By Specifies which user scheduled this result.
Generated Date-Time Generated Date-Time Specifies when this set of scheduling results was generated.
Starting Date-Time Starting Date-Time Specifies the earliest starting date-time of any production order line in this set of scheduling results.
Ending Date-Time Ending Date-Time Specifies the latest ending date-time of any production order line in this set of scheduling results.
Description Description Specifies a user-supplied description for this set of scheduling results.
Order Lines Order Lines Specifies the count of the number of production order lines in this result.
Unscheduled Order Lines Unscheduled Order Lines Specifies the number of production order lines have operations that are not scheduled. If more than zero (0) operations of a production order line are unscheduled, that production order line is flagged as unscheduled.
Late Order Lines Late Order Lines Specifies how many late production order lines are in this result.
Early Order Lines Early Order Lines Specifies how many early production order lines are in this result.
Total Setup Time (Hours) Total Setup Time (Hours) Specifies the total setup time in hours in this set of results.
Total Run Time (Hours) Total Run Time (Hours) Specifies the total run time in hours in this set of results.
Total Setup Time Total Setup Time Specifies the total setup time in this set of results.
Total Run Time Total Run Time Specifies the total run time in this set of results.
On-Time Lines On-Time Lines Specifies how many production order lines are on time in this result.
Active Active Specifies whether or not this scheduling result set is active. Only one result can be active.
Applied To Prod. Order Lines Applied To Prod. Order Lines Specifies how many production order lines this set of results has been applied to.
Apl. To Prod. Order Rtng Lines Apl. To Prod. Order Rtng Lines Specifies how many production order routing lines this set of results has been applied to.
Request Time Mode Request Time Mode Specifies the units of measure for configurable durations.

Actions:

  • Most actions in the “MxAPS Schedule Result List” apply to the selected schedule result
  • Actions that contain the word “Active” apply to the active result regardless what result may be currently selected
  • “Graph” actions will open the Gantt chart
  • Schedule Summary: clicking a “Schedule Result No.”, viewing a selected schedule result, or browsing to “MxAPS Schedule Summary” will show select details on all scheduled operations.
  • Operations can be moved to different machine centers here (note you may have to click the pencil icon to make the page editable if you opened it off a search)
  • Class, priority, and order sets can also be changed in this view
  • Note: browsing to this page from a schedule result will open the active schedule result, not the most recently generated one unless it happens to be set active.
  • “Related” button contains MxAPS scheduling result pages
  • Order Schedule: Provides the start and end time of each production order line sent for scheduling.
  • Machine Load Details: Provides details about every scheduled event on a finite capacity machine center. This is the basis for the Gantt chart and useful for troubleshooting/verification.
  • Detailed Operation Schedule: Provides details about each operation that was sent for scheduling. This is typically the data people use for most custom reporting.
  • Order Attribute Schedule: Provides information relating to how an operation was ranked. Typically not used.
  • Resource Requirements: Provides details relating to all secondary constraint usage and activities
  • Routing: Provides a consolidated page with all Prod. Order Routing Lines which is the main table MxAPS is reading for scheduling. This allows faster changing of order sets, many scheduling attributes, and enabling/disabling many heuristics from one screen rather than having to open each production order one by one.
  • Note: As with the “MxAPS Schedule Summary” browsing to these pages from a search opens the active result.
Was this article helpful?
0 out Of 5 Stars
5 Stars 0%
4 Stars 0%
3 Stars 0%
2 Stars 0%
1 Stars 0%
5
How can we improve this article?
Please submit the reason for your vote so that we can improve the article.
Need help?
Tags:

Leave A Comment

Table of Contents
Go to Top