# Skip-Lot Thresholds in Quality Inspector

Quality Inspector supports multiple ways to determine when to advance to a reduced-inspection level in a skip-lot scheme:

| **Threshold Type** | **What it Counts** | **Best Used When** |
| --- | --- | --- |
| Create Threshold | Number of tests created (or skipped). | You care about inspection frequency / workflow pacing. |
| Pass Threshold | Number of tests that successfully pass. | You care about only advancing once quality is demonstrated. |
| Fail Threshold | Number of failed tests allowed (usually 1). | You need to immediately reset to full inspection. |

Most regulatory skip-lot procedures require failures to reset the sequence, so _Fail Threshold_ is usually set to 1.

 Note: The _Pass Threshold_ field is hidden by default; you may need to personalize or customize the skip-lot sub-form to have access to this field.

### Create Threshold (Count Created/Skipped Tests)

Skip-lot step advances once a specified number of tests have been created or skipped regardless of test outcome.

Use when:

- You want to follow a schedule like “inspect every X lots”.
- You want to move forward even if tests take time to finish.
- You are not required to wait for confirmed passing results before reducing inspection.
- The main goal is to reduce workload, not enforce strict quality proof before skipping.

#### Example

“Inspect the first 10 lots, skip the next 5, and inspect 1 every so often.”

**Configuration Pattern:**

- Create Threshold: 10 → 5 → 1
- Pass Threshold: leave empty (optional)

**Industry Scenario Example:**

- Supplier consistently performs well.
- No regulatory requirement to confirm pass before reducing inspection.
- A pragmatic skip-lot program to reduce QA load.

### Pass Threshold (Count Passed Tests)

Skip-lot step advances only after [X] lots have passed inspection.

Use when:

- You must prove acceptable quality before reducing inspection.
- Lot results must be complete before advancing.

Regulatory, customer, or audit requirements demand confirmed passes

#### Example

“The first 10 lots must pass before reducing inspection frequency.”

**Configuration Pattern:**

- Pass Threshold: 10
- Create Threshold: optional (may be lower or equal)
- Fail Threshold: usually 1

**Industry Scenario Example:**

- USDA / CFR-style regulated processes.
- Pharmaceutical, medical device, or aerospace manufacturing.
- Where a failed lot must block advancement.

 Note: If testing takes time, Pass Threshold may delay advancement, which is sometimes desirable (compliance) and sometimes not (operational efficiency).

### Use Create Threshold and Pass Threshold together

You may configure **Create Threshold** and **Pass Threshold** at once. Typical pattern:

| **Scenario** | **Behavior** |
| --- | --- |
| Both set | System advances when either condition is satisfied (whichever comes first). |
| Pass only | Must wait for passes — strict compliance. |
| Create only | Strict cadence — fastest movement to skip-lot. |

### **Considerations**

- Many sites block lots (or restrict grades) so a failed lot cannot ship or be consumed. If so, waiting for passes may not be necessary; the process ensures containment anyway.
- Choose thresholds based on:

   - Regulatory requirements
   - Risk tolerance
   - Inspection cycle time
   - Operational efficiency goals