# Generate an MxAPS Schedule

The _Generate Schedule _page allows you to generate production schedules using the MxAPS scheduling engine. You start by choosing a range of production cells to schedule, then set a filter on the Production Order Routing Lines as desired. These choices determine what orders are considered during scheduling.

### Generate an MxAPS schedule

The _MxAPS Generate a Schedule_ page can be located either on the _MxAPS Production Planner_ role center or simply by searching for it.

Modify the following fields when generating a schedule:

1. Leave the _From Cell No._and _To Cell No._ fields as Main (default setting).
2. Update the _Start Date_ (set to current date and time by default).
3. Enter the _Schedule Duration_ (e.g., such as a few days, weeks, or the normal planning horizon; ensure this duration is long enough for sufficient capacity of all production orders or orders may be buffered).
4. Leave _Schedule As_ on “Unlocked” unless needed (determines if newly scheduled operations are set to be locked to the machine they were scheduled on).
5. Set a _Filter_ if needed (e.g., limit which _Order Routing Lines_are included such as filter by production order status, item, or routing status).
6. Select a _Scheduling Filter Set_ if needed (use when you have saved filter sets for repeatable scheduling scenarios).
7. Enter _Global Lead Time_if needed (use for items configured to use the global fence type).
8. Select _Consider Manual Changes From_ if needed (use to run a new schedule to consider machine moves from a previous schedule result; sets the schedule result that manual moves should be read from).
9. Select **Generate Schedule**.

Sends information from Business Central to the MxAPS Scheduling engine, returning results when finished. Review the results for accuracy or if any further adjustments may be required prior to updating Production Orders.

#### Demo

[Video: MxAPS Automated Production Scheduling – Comprehensive Overview](https://www.youtube.com/watch?v=PWYwppTUUeI)

### Review the schedule result

After the schedule is generated, open _MxAPS Schedule Result List_ to review historical schedule results. This page shows values such as generated date-time, scheduled by, starting date-time, ending date-time, order lines, order performance (unscheduled order lines, late order lines, early order lines), total setup time, and total run time.

Open a schedule result to view the _MxAPS Schedule Summary_. This page includes the _Machine Schedule Summary_ and actions to inspect the result in more detail.

 Note: MxAPS schedules only the production order routing lines included in the schedule run. If related orders share material or capacity, schedule them together so MxAPS can consider the full picture. Note: MxAPS schedules forward from the schedule start date. Due dates affect priority and lateness analysis, but the schedule is not generated backward from the due date.