# How to identify which production orders are shown in the Machine Schedule Summary

## Viewing the Production Orders Behind the Machine Schedule Summary

The Machine Schedule Summary provides a graphical overview of scheduled operations.

If you need additional information about an operation, you can drill into the underlying Production Order.

### To inspect an operation

1. Open the Machine Schedule Summary.
2. Select the operation.
3. Open the related Production Order.
4. Review the routing lines and operation details.

This allows planners to investigate:

- which production order owns the operation
- routing sequence
- scheduling dates
- operation dependencies