This article is intended to help troubleshoot the following errors:
Error when calculating backward. Calendar is not available before [Date] for Machine Center [Machine Center].
Error when calculating forward. Calendar is not available after [Date] for Machine Center [Machine Center].
Error when calculating backward. Calendar is not available before [Date] for Work Center [Work Center].
Error when calculating forward. Calendar is not available after [Date] for Work Center [Work Center].
These errors occur when Business Central cannot schedule the production operation because the required calendar does not cover the necessary date range.
These are base Business Central scheduling errors, they can occur when refreshing a production order, or when using planning tools such as Graphical Scheduler to drag and drop.
Why This Happens
Business Central schedules production operations using the calculated calendars for Work Centers and Machine Centers.
If the required calendar has not been calculated far enough backward or forward, Business Central cannot determine when the operation can run.
This can also prevent a production order from refreshing successfully. If routing lines are not created, Graphical Scheduler has no production routing lines to display.
Calculate the Work Center Calendar
- In Business Central, search for Work Centers.
- Choose Calculate Work Center Calendar.
- Enter a Starting Date and Ending Date that cover the required production period.
- Choose OK.
It is usually best to calculate enough calendar coverage before and after the expected production dates rather than using only the exact date shown in the error.
Calculate the Machine Center Calendar
If the routing uses Machine Centers, calculate those calendars as well.
- Search for Machine Centers.
- Choose Calculate Machine Center Calendar.
- Enter the appropriate Starting Date and Ending Date.
- Choose OK.
After calculating the calendars, return to the production order and run Refresh Production Order again.
Check the Shop Calendar
If the calculated calendars already cover the required date range, review the Shop Calendar assigned to the affected Work Center.
Check:
- Working days
- Shift start and end times
- Holidays
- Unexpected non-working periods
After changing the Shop Calendar, recalculate the Work Center and Machine Center calendars.
Check Holidays and Absences
A holiday or resource absence can remove available capacity from a date range.
Review:
- Shop Calendar Holidays
- Work Center absences
- Machine Center absences
- Maintenance or downtime entered for the wrong dates
Check the Date Shown in the Error
If the error references a date earlier than expected, Business Central may be scheduling the operation backward from the production order due date.
Routing values such as:
- Setup Time
- Run Time
- Wait Time
- Move Time
- Queue Time
can require an operation to begin earlier than the production order due date.
If the error date is much earlier or later than expected, review the production order dates and routing times before extending the calendar unnecessarily.
Why This Can Make Graphical Scheduler Appear Empty
Graphical Scheduler displays production routing lines created by Business Central.
If refreshing the production order fails because of a calendar error:
- Business Central cannot finish scheduling the production order.
- Production routing lines may not be created.
- Graphical Scheduler has nothing to display.
Resolve the Business Central calendar error first, refresh the production order, and then refresh or reopen Graphical Scheduler.
Troubleshooting Checklist
- Calculate the Work Center Calendar for the required date range.
- Calculate the Machine Center Calendar for the same period.
- Verify the assigned Shop Calendar.
- Check Shop Calendar Holidays.
- Check Work Center and Machine Center absences.
- Review routing and queue times if the requested date looks unexpected.
- Refresh the production order again.
- Confirm that routing lines are created before troubleshooting Graphical Scheduler further.
References
Set up shop calendars – Microsoft Learn
Set up work centers and machine centers – Microsoft Learn
How to Visualize Work Center Capacity and Load in Graphical Scheduler