# How to Visualize Work Center Capacity and Load in Graphical Scheduler

## How to Visualize Work Center Capacity and Load in Graphical Scheduler

Graphical Scheduler from Insight Works can display Business Central work center capacity and load directly on the schedule. This provides production planners with a visual indication of which work centers have available capacity, which are approaching capacity, and which may be overloaded.

The visualization uses the work center calendar and production capacity requirements calculated by Business Central. Before configuring the visualization in Graphical Scheduler, make sure that Business Central has calculated capacity for the period that you want to display.

### Understanding Work Center Capacity and Load

In Business Central:

- **Capacity** represents the amount of work that a work center can perform during a period.  This is in the unit of measure configured on the work center.
- **Allocated Qty.** represents the capacity required by production order operations during that period.
- **Availability After Orders** is the remaining capacity after the allocated production requirements are considered.
- **Load** represents the allocated capacity as a percentage of the effective capacity.

For example, a work center with 1,440 minutes of capacity and 365 minutes allocated has approximately **25.3% load** and **1,075 minutes available after orders**.

Business Central calculates work center capacity from information including the assigned Shop Calendar, the work center’s Capacity, and Efficiency.

### Prepare Work Center Capacity in Business Central

If you are configuring a demonstration, training, or test environment, first make sure that capacity has been calculated for the dates that you intend to show.

1. Search for **Work Centers** in Business Central.
2. Open the required work center.
3. Verify the **Shop Calendar Code**, **Unit of Measure Code**, **Capacity**, and **Efficiency**.
4. Calculate the Work Center Calendar for the required date range.
5. If production routing operations use machine centers, also calculate the calendars for the applicable machine centers.

You can verify the results from the Work Center Card by choosing **Load** and setting **View by** to **Day**.

Microsoft provides additional information about calculating work center calendars here:

[Set up shop calendars in Business Central](https://learn.microsoft.com/en-nz/dynamics365/business-central/production-how-to-create-work-center-calendars?utm_source=chatgpt.com)

### Example Capacity Setup

The following example uses CRONUS demonstration data and Work Center **100 – Assembly Department**.

The example uses:

| Setting | Value |
| --- | --- |
| Work Center | 100 – Assembly Department |
| Unit of Measure Code | Minutes |
| Shop Calendar Code | 1 – One shift Monday-Friday |
| Capacity | 3 |
| Working Hours | 08:00-16:00 |
| Working Days | Monday-Friday |

The shop calendar provides eight working hours per day:

| Day | Starting Time | Ending Time | Work Shift Code |
| --- | --- | --- | --- |
| Monday | 08:00 | 16:00 | 1 |
| Tuesday | 08:00 | 16:00 | 1 |
| Wednesday | 08:00 | 16:00 | 1 |
| Thursday | 08:00 | 16:00 | 1 |
| Friday | 08:00 | 16:00 | 1 |

With a capacity of 3 and 100% efficiency, this produces:

**8 hours × 60 minutes × 3 = 1,440 minutes of effective daily capacity.**

After calculating the Work Center Calendar, a period with no production orders might appear as follows:

| Period Start | Period Name | Capacity | Allocated Qty. | Availability After Orders | Load |
| --- | --- | --- | --- | --- | --- |
| 2026-08-09 | Sunday | 0 | 0 | 0 | 0 |
| 2026-08-10 | Monday | 1,440 | 0 | 1,440 | 0 |
| 2026-08-11 | Tuesday | 1,440 | 0 | 1,440 | 0 |
| 2026-08-12 | Wednesday | 1,440 | 0 | 1,440 | 0 |
| 2026-08-13 | Thursday | 1,440 | 0 | 1,440 | 0 |
| 2026-08-14 | Friday | 1,440 | 0 | 1,440 | 0 |
| 2026-08-15 | Saturday | 0 | 0 | 0 | 0 |

> **Tip:** If Graphical Scheduler shows no available capacity for a period that should contain working time, verify the Work Center Calendar in Business Central first. Graphical Scheduler relies on the capacity calculated by Business Central.

### Add Production Load

Next, create or use production orders whose routing operations fall within the calculated calendar period.

For example, a production order for four units of CRONUS item **1000 – Bicycle** could have the following routing:

| Production Order No. | Operation No. | Type | No. | Description | Starting Date-Time | Ending Date-Time | Setup Time | Run Time |
| --- | --- | --- | --- | --- | --- | --- | --- | --- |
| 1011010 | 10 | Work Center | 100 | Wheel assembly | 2026-08-21 09:55 | 2026-08-21 12:33 | 110 | 12 |
| 1011010 | 20 | Machine Center | 120 | Chain assembly | 2026-08-21 12:33 | 2026-08-21 13:48 | 15 | 15 |
| 1011010 | 30 | Machine Center | 130 | Final assembly | 2026-08-21 13:48 | 2026-08-21 15:18 | 10 | 20 |
| 1011010 | 40 | Machine Center | 110 | Control | 2026-08-21 15:18 | 2026-08-21 16:00 | 10 | 8 |

After the production order is scheduled, return to **Work Center > Load**.

For this example, the load on August 21 is:

| Period Start | Period Name | Capacity | Allocated Qty. | Availability After Orders | Load |
| --- | --- | --- | --- | --- | --- |
| 2026-08-17 | Monday | 1,440 | 0 | 1,440 | 0 |
| 2026-08-18 | Tuesday | 1,440 | 0 | 1,440 | 0 |
| 2026-08-19 | Wednesday | 1,440 | 0 | 1,440 | 0 |
| 2026-08-20 | Thursday | 1,440 | 0 | 1,440 | 0 |
| 2026-08-21 | Friday | 1,440 | 365 | 1,075 | 25.3 |
| 2026-08-22 | Saturday | 0 | 0 | 0 | 0 |

The resulting load is approximately:

**365 ÷ 1,440 × 100 = 25.3%**

You can drill into **Availability After Orders** in Business Central to see the production capacity requirements contributing to the calculation.

For this example:

| Type | No. | Starting Date-Time | Ending Date-Time | Time Type | Allocated Time |
| --- | --- | --- | --- | --- | --- |
| Work Center | 100 | 09:55 | 11:45 | Setup Time | 110 |
| Work Center | 100 | 11:45 | 12:33 | Run Time | 48 |
| Machine Center | 120 | 12:33 | 12:48 | Setup Time | 15 |
| Machine Center | 120 | 12:48 | 13:48 | Run Time | 60 |
| Machine Center | 130 | 13:48 | 13:58 | Setup Time | 10 |
| Machine Center | 130 | 13:58 | 15:18 | Run Time | 80 |
| Machine Center | 110 | 15:18 | 15:28 | Setup Time | 10 |
| Machine Center | 110 | 15:28 | 16:00 | Run Time | 32 |

Microsoft provides more information about reviewing this information in Business Central here:

[View load on work and machine centers](https://learn.microsoft.com/en-us/dynamics365/business-central/production-how-to-view-the-load-on-work-centers?utm_source=chatgpt.com)

### Display Work Center Load in Graphical Scheduler

Once Business Central is calculating the expected capacity and load, add the Work Center Load data source to a Graphical Scheduler view.

1. Start **Graphical Scheduler**.
2. Choose **View**.
3. Select a view that contains production data. Alternatively, create a new view using the standard **PRODUCTION** data source for production order routing lines.
4. Edit the view.
5. From the **Graphical Scheduler View** card, choose **Add a Data Source**.
6. Select **All Work Center Load**.

Graphical Scheduler adds the **WRKLOAD** data source to the view.

The standard Work Center Load data source includes the following data fields:

- Load
- Available
- Effective
- UOM

The default cell template is:

`[Load] - [Available]/[Effective]`

The default tooltip is:

`Load= [Load]` `Effective = [Effective] [UOM]` `Available = [Available] [UOM]`

These are the defaults created by the **All Work Center Load** configuration option.

For the previous example, Graphical Scheduler displays a cell similar to:

**25.3 – 1075/1440**

This corresponds directly to the Business Central load information:

- **Load:** 25.3%
- **Available:** 1,075 minutes
- **Effective Capacity:** 1,440 minutes

### How the Time Scale Affects Load

Work Center Load is calculated for the time periods displayed by the Graphical Scheduler view.

For example, if the view uses the **Next 2 weeks** date preset with a **Day and Week** time scale, work center capacity and load are displayed in daily periods.

Changing to a larger time scale can cause capacity and load to be summarized into larger periods. This is useful when planners want to review capacity at different planning horizons rather than only by individual day.

To ensure reasonable performance:

- The tool does not display all work center load when looking at very large time horizons.
- The tool will only display work center load for the Hours, Day, Week, and Month time scales.

### Work Center Load Colors

When the **All Work Center Load** data source is added, Graphical Scheduler also creates three default styles:

| Style | Filter | Background Color |
| --- | --- | --- |
| OVER | `Load > 95` | Light Red |
| UNDER | `Load = 25..95` | Blue Gray |
| UNSCHEDULED | `Load < 25` | Light Orange |

These styles are available from **Configure Styles In This View** and can be modified to match your organization’s preferred capacity thresholds and colors.

Using the earlier example, a load of **25.3%** matches the **UNDER** style, so the work center load cell is displayed with a blue-gray background.

If additional production orders are scheduled onto the same work center and period, the load percentage increases. When the load exceeds **95%**, the default **OVER** style changes the cell to light red.

This makes it possible to identify heavily loaded work centers visually without opening the individual Work Center Load pages in Business Central.

### Using the Visualization for Production Planning

Work Center Load visualization is useful for quickly identifying:

- Work centers with significant unused capacity.
- Work centers approaching their available capacity.
- Work centers that may be overloaded.
- Days or periods where moving an operation could improve the production schedule.
- Differences between the available working calendar and the production work currently allocated to it.

The visualization does not replace Business Central’s manufacturing capacity calculations. Graphical Scheduler presents the calculated capacity and production requirements visually so that planners can more easily identify periods that require attention.

### Related Information

For more information, see:

- [Graphical Scheduler – Setup Guide](/kb/graphical-scheduler/graphical-scheduler-setup-guide/)
- [Set Up Shop Calendars – Microsoft Business Central](https://learn.microsoft.com/en-nz/dynamics365/business-central/production-how-to-create-work-center-calendars?utm_source=chatgpt.com)
- [View Load on Work and Machine Centers – Microsoft Business Central](https://learn.microsoft.com/en-us/dynamics365/business-central/production-how-to-view-the-load-on-work-centers?utm_source=chatgpt.com)

![Example of work center load with three different example articles.](/wp-content/uploads/kb-legacy/Screenshot-2026-08-20-141822-800x322.png)