# How to Plan Purchases for Demand Across Multiple Locations

When an item is replenished through multiple locations, use a two-step planning process:

1. **Can the demand be supplied from another location?**
2. **What must be purchased after the transfers are considered?**

Keeping these stages separate makes the planning results easier to review and clearly distinguishes internal transfers from external purchases.

### Example

One item has four Stockkeeping Units:

- **SKU 1:** Replenishment System = Transfer; supplied from SKU 4’s location
- **SKU 2:** Replenishment System = Transfer; supplied from SKU 4’s location
- **SKU 3:** Replenishment System = Transfer; supplied from SKU 4’s location
- **SKU 4:** Replenishment System = Purchase

Demand forecasts exist for SKU 1, SKU 2, and SKU 3. SKU 4 has no direct forecast because its demand is created by the transfer orders supplying the other locations.

### Step 1: Plan the transfers

In order to keep a clear distinction of actions, a separate Transfer batch could be created. This keeps transfer proposals separate from purchase proposals. You can configure a separate transfer planning batch in **Enhanced Planning Worksheet User Preferences**, accessible via the “User Preferences” action from the Enhanced Planning Worksheet.

1. Open the **Enhanced Planning Worksheet** using the transfer batch.
2. Select **Calculate Purchase Plan**.
3. Set **Plan replenishment for** to **Transfer Only**.
4. Select the Batch you wish to populate, as noted this could be a dedicated Transfer Batch.
5. Run the calculation.
6. Review the proposed transfers for SKU 1, SKU 2, and SKU 3.

 Note: If additional inventory visibility is needed, configure the Inventory Location Filter in the Enhanced Planning Worksheet User Preferences. This allows you to view on-hand inventory from other locations in the Planning Summary Fact Box and evaluate whether the recommended Transfer Orders should be modified.

1. Select **Carry Out Action Message** to create the transfer orders.

The transfer orders now represent actual demand against SKU 4’s supplying location.

> The first planning question is: “Can I take this inventory from somewhere else?”

### Step 2: Plan the purchases

After the transfer orders have been created, calculate the remaining purchase requirements.

#### Use Calculate Purchase Plan when:

- Purchase demand should be simplified and consolidated.
- A single combined purchase quantity is preferred.
- Detailed demand dates and order tracking are not required.

Open the purchase batch, select **Calculate Purchase Plan**, and set **Plan replenishment for** to **Non-Transfer Only** or **Purchase And Transfer Only**, as appropriate.

In this example, the calculation produces one purchase proposal for SKU 4 based on the demand from the three transfer orders.

For more information on how the Enhanced Planning Worksheet “Calculate Purchase Plan” works refer to [https://kb.dmsiworks.com/knowledge-base/how-does-the-planning-worksheet-purchase-plan-calculate-the-amount-to-purchase/](/kb/enhanced-planning-pack/how-does-the-planning-worksheet-purchase-plan-calculate-the-amount-to-purchase/)

#### Use Calculate Regenerative Plan when:

- Demand must be planned by individual requirement date.
- Multi-level or date-sensitive planning is required.
- Purchase requirements should not be consolidated by the simplified Purchase Plan calculation.

From the **Enhanced Planning Worksheet**, select **Calculate Regenerative Plan** and apply the appropriate item and location filters.

> The second planning question is: “After using available inventory from other locations, what do I need to purchase?”

### Why two calculations are required

**Calculate Purchase Plan** does not use newly proposed transfer worksheet lines as demand at the supplying location during the same calculation. The transfer proposals must first be carried out into transfer orders. A second planning calculation can then recognize those transfer orders as demand and calculate the related purchase requirement.