Calculate Purchase Plan can create planning BOMs for production suggestions and use their material requirements to suggest replenishment for lower-level components.
Use this when you want to review production requirements alongside purchasing recommendations, or plan finished goods, subassemblies, and purchased materials in the same run. This may not support all of the same scenarios as “Calc. Regen. Plan”.
The calculation creates worksheet suggestions. Actual production, purchase, and transfer orders are created after you review the suggestions and run Carry Out Action Message.
Before you begin
You should be familiar with Business Central production BOMs, stockkeeping units, and planning worksheet suggestions.
Check that:
- Extended Purchase Planning is enabled in Enhanced Planning Worksheet Setup.
- A stockkeeping unit exists for every item, location, and variant you want to plan.
- Each SKU has an appropriate Replenishment System, Reordering Policy, and stocking parameters.
- Production items have valid, certified production BOMs.
- Routings and work or machine center calendars are configured where routing calculation is required.
- Item low-level codes are current. Run Calculate Low-Level Code after changing the BOM structure if necessary.
Component planning respects the selected SKU filters. It does not automatically add missing SKUs or include components excluded by item, location, vendor, or replenishment filters.
Choose the production-planning behavior
On Run Purchase Plan, set Production Planning:
| Option | Business impact |
|---|---|
| Disabled | Creates replenishment suggestions without automatically creating planning BOMs or routing operations. This feature adds no planning-component demand. |
| Create Planning BOM | Creates planning components for new production suggestions so you can review their material requirements. Those requirements do not generate additional component suggestions during this run. |
| Create Planning BOM and Plan Components | Creates planning components and includes their requirements when calculating replenishment for eligible component SKUs in the same run. |
With Create Planning BOM, a component can still receive a suggestion because of its own sales demand, safety stock, or other planning requirements. The distinction is that the newly created planning BOM does not drive that component’s replenishment.
Choose whether to calculate routings
Routing Calculation applies when production planning is enabled.
| Option | Business impact |
|---|---|
| Do Not Calculate | Creates planning components without creating planning routing operations. Use this when material quantities are required without a calculated operation schedule. |
| Calculate | Creates planning routing operations and schedules production backward from the suggestion’s ending date using routing times and the applicable calendars. |
Do Not Calculate does not freeze dates, but it does not provide the same production schedule as Calculate. Production starting dates may remain at their initialized dates rather than showing a separate manufacturing duration for every level.
Routing Link Code limitation: Not all routing link component support exists, consider using “Calc. Regen. Plan” or refreshing planning lines if you are using routing link codes.
Run the plan
- Open Enhanced Planning Worksheet.
- Select Prepare → Calculate Purchase Plan.
- Set Plan replenishment for to include all required replenishment systems. For a mixture of production and purchased items, select All.
- Select the required Production Planning option.
- Select Routing Calculation.
- Set Include Planned Items according to whether existing worksheet suggestions should participate in the calculation.
- Select the destination batch and review Existing Worksheet Lines.
- Apply SKU filters that include both the production items and their required components.
- Select OK.
Defaults for Production Planning and Routing Calculation can be configured in Enhanced Planning Worksheet Setup. Review the choices on the request page before each run.
Existing and newly created planning components
With Create Planning BOM and Plan Components:
- Planning BOM requirements created during the current run are considered even when Include Planned Items is set to Exclude.
- Retained planning-component requirements from existing worksheet suggestions are considered only when planned items are included.
- Existing inventory, included supply, stocking parameters, and order modifiers still affect the resulting quantities.
When excluding planned items, review retained worksheet lines carefully to avoid processing duplicate supply suggestions.
Example: finished good, two subassemblies, and shared raw material
Create the following items and SKUs at the same location:
| Item | Replenishment System | Manufacturing Policy | Reordering Policy | Safety Stock Quantity |
|---|---|---|---|---|
| EPW-C-FG | Prod. Order | Make-to-Stock | Lot-for-Lot | 10 |
| EPW-B-SUB | Prod. Order | Make-to-Stock | Lot-for-Lot | 0 |
| EPW-E-SUB | Prod. Order | Make-to-Stock | Lot-for-Lot | 0 |
| EPW-A-RAW | Purchase | — | Lot-for-Lot | 0 |
Configure these production BOM lines:
| Parent | Component | Quantity Per |
|---|---|---|
| EPW-C-FG | EPW-B-SUB | 2 |
| EPW-B-SUB | EPW-E-SUB | 2 |
| EPW-B-SUB | EPW-A-RAW | 3 |
| EPW-E-SUB | EPW-A-RAW | 2 |
For this example, assume there is no inventory, existing supply, other demand, scrap, or order modifier that changes the quantities.
Run Purchase Plan for all four SKUs using:
- Plan replenishment for: All.
- Production Planning: Create Planning BOM and Plan Components.
- Routing Calculation: Calculate, with valid routings and calendars.
- Include Planned Items: Exclude.
- Plan items with demand only: Off.
- An empty test batch.
Expected suggestions are:
| Item | Quantity | Explanation |
|---|---|---|
| EPW-C-FG | 10 | Replenishes finished-good safety stock. |
| EPW-B-SUB | 20 | 10 finished goods × 2. |
| EPW-E-SUB | 40 | 20 subassemblies × 2. |
| EPW-A-RAW | 140 | Direct requirement of 20 × 3, plus lower-level requirement of 40 × 2. |
The three independently planned Make-to-Stock production suggestions should have separate Ref. Order No. values.
Understand the suggested dates
Component planning processes parent items before their lower-level components.
When positive net planning-component demand exists, its earliest dated positive requirement can bring the component suggestion’s due date forward. A receipt date that is already earlier is retained.
With Routing Calculation = Calculate, production operations are scheduled backward from the production suggestion’s ending date. Without routing links or lead-time offsets, components are normally required at their parent’s starting date.
When component demand brings a purchased suggestion’s receipt forward, its starting date is calculated backward using the standard purchasing lead-time and calendar logic, including applicable safety and warehouse-handling time.
Dates can fall before the work date when that is when supply needed to start. Review these suggestions for feasibility. Order Date follows the standard behavior of your Business Central version and should not be assumed to equal Starting Date.
Purchase Plan still consolidates demand into one suggestion per SKU. For example, all 140 raw-material units in this example may be suggested for the earliest applicable requirement date, even though different parents need portions of that quantity on different dates.
Review and create orders
After calculation:
- Review quantities, due dates, starting dates, and replenishment systems.
- Open the production suggestions’ Planning Components to review material requirements.
- Review Planning Routing when routing calculation was enabled.
- Confirm that the required component SKUs received suggestions.
- Review Accept Action Message.
- Run Carry Out Action Message to create the required supply orders.
Use Calculate Regenerative Plan when you need the standard time-phased MPS/MRP calculation, including supply and demand balancing across multiple dates. Optional component planning extends Purchase Plan’s consolidated SKU calculation; it does not turn it into the full regenerative planning engine.
Still need help?
Ask other Business Central users in the Insight Works community, or send the details to the support team. Include the steps you took and any error message you saw.