# Analyzing Production Order Variances with Production Order Analysis

The **Production Order Analysis Worksheet** feature in Enhanced Planning Pack helps you compare the expected and actual results of a production order. It is useful for investigating differences in material consumption, setup time, run time, and production costs.

For more higher level details refer to [https://dmsiworks.com/apps/production-order-analysis](https://dmsiworks.com/apps/production-order-analysis)

Production Order Analysis was added to Enhanced Planning Pack in version 3.4, and resides within the Routing Analysis app within the Enhanced Planning Pack.

## Why use the Production Order Analysis Worksheet?

Use Production Order Analysis when you need to answer questions such as:

- Did the production order consume more material than expected?
- Did an operation take longer than planned?
- Was the actual production cost higher than expected?
- Which component or routing operation contributed to the variance?

The worksheet presents the production order as a hierarchy of items, components, and routing operations.

## Open Production Order Analysis

Search for **Production Order Analysis Worksheet** in Business Central.

At the top of the worksheet, select:

1. **Status** – select the production order status.
2. **No.** – select the production order.
3. **Line No.** – optionally select a specific production order line.

Leaving the Line No. blank analyzes the production order rather than a single production order line.

## Analyze component consumption

For production components, compare:

- **Component Quantity (Expected)**
- **Component Quantity (Actual)**
- **Component Quantity (Variance)**

These values help identify components that were consumed differently than expected.

You can drill down on the Expected and Actual quantities to review the supporting information.

## Analyze setup time

For routing operations, compare:

- **Routing Setup Time (Expected)**
- **Routing Setup Time (Actual)**
- **Routing Setup Time (Variance)**

Use these fields to identify operations where actual setup time differed from the expected setup time.

The Expected and Actual values support drilldown for further investigation.

## Analyze run time

Similarly, compare:

- **Routing Run Time (Expected)**
- **Routing Run Time (Actual)**
- **Routing Run Time (Variance)**

This is useful when investigating production orders that required more or less processing time than planned.

## Analyze production costs

Production Order Analysis also includes expected, actual, and variance information for production costs, including:

- Material cost
- Capacity cost
- Subcontracting cost
- Capacity overhead cost
- Total cost

Both single-level and rolled-up cost information is available where applicable.

The analysis can also include **Sales Amount**, **Gross Margin Amount**, and **Gross Margin %**.

## Drill down into a variance

Several Expected and Actual values on the worksheet support drilldown.

When a value appears unexpected, drill into it to review the records contributing to the calculated result. This is particularly useful when investigating material consumption or routing-time differences.

## Print the Production Order Analysis Report

Enhanced Planning Pack also includes the **Production Order Analysis Report**.

The report can show:

- Units
- Actual costs
- Expected costs
- Cost variances
- Sales and margin information

You can select the production order status, production order number, and optionally a production order line before running the report.

## Production Order Analysis vs. Routing Analysis

Use the **Production Order Analysis Worksheet** when investigating the results of a particular production order.

Use **Routing Analysis** when analyzing routing performance across production activity to identify production-time variation and trends. Routing Analysis is a separate feature within Enhanced Planning Pack.

## Example: investigating excess production hours

If a production order appears to have taken longer than expected:

1. Open **Production Order Analysis Worksheet**.
2. Select the finished production order.
3. Locate the relevant routing operation.
4. Compare **Routing Setup Time (Expected)** with **Routing Setup Time (Actual)**.
5. Compare **Routing Run Time (Expected)** with **Routing Run Time (Actual)**.
6. Review the corresponding variance fields.
7. Drill into the Expected or Actual values when additional detail is required.

This provides a direct way to identify where the recorded production time differed from the expected routing time.

![Production Order Analysis example](/wp-content/uploads/kb-legacy/Producton-Order-Analysis-002-800x450.png)